Job Schedule
This is my project schedule. It has been modified, because in the while I found some issues, and took me more time to solve them.
Tasks |
Deadline |
Progress |
1. Basic Web Interface |
June 26th |
100% |
2. Javascript Functions to translate normal text to Mallard |
July 10th |
100 % |
3. Generation of Mallard Syntax document with Python / PHP |
July 17th |
100 % |
4. Integration with GIT |
I'll finish after GSoC |
0 % |
5. System complete and debugged |
I'll finish after GSoC |
0% |