Aline Bessa

Email: <alibezz AT gmail DOT com>

Timeline for my internship (GNOME Women 2011)

  • Create one demonstration widget/simple app (4 weeks)
    • Define the widget/app theme and scope with my mentors and a11y team's contributions (1 day)
    • Discuss and plan a good way of implementing it, besides listing which libs should be used (2 days)
    • Install and familiarize with libs used (2 days)
    • Develop widget/app (2 weeks)
    • Test and synchronize the widget app with the a11y team (1 week)
  • Convert the Accerciser docs into topic-based help (2 weeks)
    • Review and rewrite the Accerciser docs using Mallard and making use of previous topic notes, besides a11y team's contributions (10 days)
    • Submit the generated documentation to preliminary reviews and synchronizations by the a11y team (4 days)
  • Create a second demonstration widget/simple app (3 weeks)
    • Define the widget/app theme and scope with my mentors and a11y team's contributions (1 day)
    • Discuss and plan a good way of implementing it; it would be good to reuse/explore the first app/widget as much as possible (2 days)
    • Install and familiarize with libs used (1 day, since I may reuse much of what I've learnt with the first widget/app)
    • Develop widget/app (10 days)
    • Test and synchronize the widget app with the a11y team (1 week)
  • Update the developer docs for accessibility implementations (3 weeks)
    • Review, revise and update informations (1 week)
    • Add more information/examples based on my experience throughout the previous 2 months (widgets/apps included) (1 week)
    • Submit the generated documentation to preliminary reviews and synchronizations by the a11y team (1 week)


CategoryHomepage

AlineBessa (last edited 2011-05-10 02:13:42 by AlineBessa)